What a GC Should Ask a Millwork Sub on a Public Works Job
A ten-question checklist for choosing a commercial millwork sub on a school, clinic, city building or other publicly funded project.

On a public works job, the cabinet and millwork package is a small line item with a long paper trail. A sub who can build beautiful casework but can't produce a clean compliance package can stall your payment application, your closeout, or your whole schedule.
This checklist is for general contractors and procurement staff. Use it when you are choosing a commercial millwork sub for a school, clinic, city building or other publicly funded project. Ask for answers in writing, and ask early, before the bid is leveled.
At California Woodworking, about 25% of our projects are prevailing wage, so these are questions we are used to answering. We have put our own answers next to each one so you can see what a straight answer looks like.
1. Are you licensed, and are you registered with DIR?
Public works in California requires a current contractor license and registration with the Department of Industrial Relations (DIR). Ask for both numbers and check them yourself.
- What to look for: A license in the right classification (C-6 covers cabinet, millwork and finish carpentry) and an active DIR registration number.
- Our answer: CA license 597445 C-6; DIR registration #1000007557.
2. Are you bonded, and what is your capacity?
"Bonded contractor" gets used loosely. Ask for the actual single-project and aggregate limits, and compare them to the subcontract value and to the work the sub already has open.
- What to look for: Single-project and aggregate capacity that fits your scope, and whether the sub will be asked for a performance and payment bond on your contract.
- Our answer: Bonding capacity is $500,000 single project and $500,000 aggregate. If your subcontract needs more, tell us before bid day so we can talk it through.
3. What insurance do you carry?
Ask for current certificates, not a verbal summary, and read them against the contract's insurance requirements.
- What to look for: General liability, umbrella or excess, workers' compensation and commercial auto, with limits that meet your contract.
- Our answer: $1,000,000 each for general liability, umbrella/excess, workers' compensation and commercial auto. If your contract calls for higher limits or specific endorsements, send the requirements with the bid invitation and we will tell you what we can meet.
4. Who handles certified payroll, and how is it submitted?
Prevailing wage projects require certified payroll records to be filed electronically with DIR, on schedule. Late or missing reports can hold up payment.
- Ask: Who prepares the reports, what system do they use, and how do you get copies for your own file?
- Our answer: We handle certified payroll and DAS 140 apprentice reporting in-house, so there is one person to call.
For a deeper look at how the rules work, see our guide: Prevailing Wage Projects: What Contractors Need to Know.
5. How do you handle apprentices (DAS 140)?
Apprentice use and reporting is a common compliance gap. Ask whether the sub knows the ratio requirements for the trade and who files the DAS 140.
6. Is your installation crew safety-trained?
Ask about the crew that will actually be on your site, not the company's general safety statement.
- What to look for: OSHA 10 cards for installers, and a willingness to follow your site safety plan and attend your coordination meetings.
- Our answer: Every installer on our crew holds OSHA 10 certification.
7. How do you handle shop drawings and submittals?
On institutional work, nothing gets built until the architect approves it. A sub who is late on submittals puts your schedule at risk before any lumber is cut.
- Ask: Do you produce complete shop drawings on every job? Who is the contact for RFIs? How quickly do you turn around resubmittals?
- Our answer: Every project gets custom shop drawings and a dedicated project manager who also handles field measurement and coordination. We are also Woodwork Institute certified, which gives the architect a recognized quality standard to review against.
8. What is the realistic schedule?
Ask for a schedule that separates submittals, material procurement, fabrication and installation, rather than one overall number.
- What to look for: A sub who tells you what is outside their control (approval time, material lead times, site readiness) and what they need from you.
- Our answer: A typical project runs about 10 weeks from consultation to installation, and a basic scope can be fabricated in about three weeks, not counting submittals and installation. We will give you a project-specific schedule, not a generic one.
9. What do you provide at closeout?
Closeout is where public work slows down. Ask what documents the sub provides, and when.
- What to look for: As-builts, care and maintenance instructions, warranty documents, and any certified payroll or compliance records your owner requires.
- Our answer: We provide as-builts, care instructions and warranty documents, and we back installed products with a one-year warranty.
10. What are the payment, retention and release terms?
Read this part of the subcontract with the sub before signing. Ask how and when billing happens, how retention is handled, and what lien or stop-payment-notice releases you need with each payment application.
- What to look for: Clear billing milestones, retention terms that match the prime contract, and a sub who submits releases with each pay application without being chased.
- Our answer: Send us your pay application and release requirements up front, and we will build them into our billing from the first invoice.
GC quick checklist
Copy this into your prequalification form:
- CA contractor license number and classification (C-6 for millwork)
- DIR registration number
- Single-project and aggregate bonding capacity
- Current certificates for GL, umbrella, workers' comp and auto
- Certified payroll process and DAS 140 contact
- OSHA 10 cards for installers
- Shop drawing and submittal turnaround
- Schedule broken into submittals, procurement, fabrication and installation
- Closeout document list
- Payment, retention and release terms agreed
Frequently asked questions
What is the difference between a millwork sub and a casework sub?
Casework refers to built-in cabinets and storage units. Millwork is the broader term and also covers items like reception desks, paneling and trim. Most public works packages include both. See our pages on commercial millwork and commercial casework.
Does a government contractor have to be bonded?
It depends on the project and the contract. Many public works contracts require bonding at the prime level, and some pass requirements down to subs. Read the subcontract and ask your bonding agent. The point of asking a sub for capacity is to know they can finish the work they take on.
What does prevailing wage mean for a millwork package?
Workers must be paid at least the wage rate set by DIR for the classification and county, and the sub must submit certified payroll records. It affects pricing, paperwork and sometimes schedule, so ask about it before bid day.
What should I send a sub to get an accurate bid?
Send the plans, specs, addenda, bid date and prevailing wage status. Tell us which items you want priced as alternates, such as solid surface countertops or privacy panels, so that bids can be compared fairly.
A good millwork sub makes your compliance package easier, not harder. If you would like to see how we answer these questions on a real bid, we are glad to send our documents.
See our full list of government and public works requirements.